A £1.4 million project – which had been in the pipeline for six years – has reached completion.

Overseen by the Isleham Community Association, the new community centre is fantastic new facility for the whole village. The centre is a vital hub for the community and provides a mix of indoor and outdoor facilities.

Features of the new centre include a large hall, a cafe/bar, a kitchen, a conference room, changing facilities and an office for the Clerk of Isleham Parish Council. Meanwhile, outdoor facilities at the new community centre include a picnic and play area, along with car parking provisions.

Approval for the new community centre was granted by Isleham Parish Council in November 2012, with a ground breaking ceremony taking place on Saturday 8th December at 11am.

CJ Murfitt was the main contractor on the project for the village of Isleham, which saw the new centre replace a former village hall and pavilion. Isleham Parish Council initiated the construction of the new community centre after the former site – built in the 1950s – was deemed no longer fit for purpose.

 Isleham Village- Community Centre

Ingenium Archial Limited was the architect on the project, whilst Tillyard & Partners was the quantity surveyor and MLM Consulting Engineers Limited was the structural engineer. The progress of the work was monitored via a dedicated Facebook page, whilst the village website provided continued updates.

To facilitate the build a fundraising campaign was initiated in 2007, with grants and donations being provided by a number of leading organisations, including Sport England, East Cambridgeshire District Council, Garfield Weston, WREN, Amey Cespa and the Football Foundation.

Commenting on the project Football Foundation Chief Executive officer Paul Thorogood, said:

“I commend Isleham Community Association and Isleham Parish Council and the Cambs FA for working tirelessly to secure this funding.”

At the beginning of 2013 the highways entrance to the site was rebuilt, providing better access, whilst turf and topsoil was removed and a site office and portakabin was installed. Foundations were then installed in March, with only a slight delay in the programme taking place in April due to the weather.

With significantly improved weather conditions during the summer, work continued to make good progress on the community centre, with the project reaching completion in November 2013.

 Isleham Village- Community Centre

The new building includes a mix of facing brickwork and timber effect concrete cladding, dark grey uPVC double glazed windows, a Kinspan insulated steel panel roof and uPVC external doors. Safety and security was also being catered for with the installation of detection and alarm systems.

Site works on the project included the installation of a mains supply and some hard and soft landscaping.

Although the new centre was designed to become a true focal point for the village, the former village hall was not forgotten during the construction process. A series of events took place in 2013 to commemorate the former facility, which included a children’s disco, an under 18s teenage disco, a tea dance with live music and an over 18s party with live band.