Premier Rail

Carlisle Station

Carlisle Station
Written by Roma Publications

New Roof for Carlisle Station

Constructed in 1847 and originally built to serve both the Lancashire and Carlisle Railway and the Caledonian Railway, Carlisle station is a Grade II* listed building that supports an elegant glazed roof with a 50m clear span.

Sadly, over time, the roof had fallen beyond reasonable repair and investigations of the roof structure indicated that the existing steel roof trusses had sagged due to age and due to the effects of a radical shortening of the existing roof span in the 1950s. The effects of the existing rigid glazing system and the roof drainage were deemed severe, causing ponding of rainwater, leakage and breakage of multiple glazing panels.

Main contractors Galliford Try and architects Jefferson Sheard worked closely with Network Rail to provide a sensitive but contemporary roof replacement whilst preserving the original architectural aesthetic and without disruption to the ongoing rail and passenger activity below.

Delivered as part of Network Rail’s Upgrade Plan, which is the company’s response to the tremendous growth of British railway, the £14.7 million investment will significantly extend the life of the station’s roof, as well as reducing the amount of future maintenance. The new roof will also make platform areas brighter and more pleasant. It is made of ETFE (Ethylene Tetrafluoroethylene), the same material used on the roofs of the new Manchester Victoria and Birmingham New Street stations.

As part of the work, the platforms will also be safer for passengers with tactile paving marking their edges and new surfaces throughout.

The improvements were made possible thanks to a huge scaffold access deck provided by leading scaffolding contractor Palmers. The deck was installed above the tracks through the station to provide a safe area for Network Rail’s ‘orange army’ to carry out the work. The deck was 47m in span and 160m long, spanning 13 roof bays and created a working level 9m above ground level. It was created by more than 20 advanced scaffolders, with additional support by Palmers management and supervisors.

Chris Atkins, Scheme Project Manager at Network Rail, said: “Passengers are really beginning to see the transformation of Carlisle station as a result of this work. The rejuvenated roof will mean a brighter, more airy and cleaner environment which will enhance the station’s beautiful features.

“It is a significant investment into Carlisle which has not been without its challenges. The scaffolding needed to carry out the work was a feat of engineering in itself but being able to carry out the work without impacting passengers’ journeys was always our aim.

“The result is a better station which will be a fitting gateway to the historic city of Carlisle.”

John Stevenson, MP for Carlisle, said: “Carlisle’s train station is one of the most important gateways into the city. I am delighted to see the renovations have preserved the historic spirit and beauty of the building. Not only have the railways played a central role in the development of our city, but they will continue to be vital for creating greater prosperity in our future.”

The majority of the glass removed from the roof was recycled by North West Recycling LTD, based at Kingmoor Park, Carlisle. Around 120 tonnes of glass was removed from the roof and was recycled into new bottles and windows.

Carlisle Station

Photo Neil Denham www.neildenham.co.uk

Work started on the new roof on 30 November 2015 and took 15 months to complete. Work on the platforms started once the roof was completed and finished in February 2018. A total of £9.5 million was spent on the roof upgrade and a further £5.2 million was spent on the platform work.

 

 

About the author

Roma Publications