A1 Dishforth to Leeming project reaches completion

A £330 million improvement scheme on the A1 in Yorkshire has been delivered by Carillion – Morgan Sindall JV on behalf of the Highways Agency.

The aim of the project was to reduce the high levels of accidents and congestion on the route and enhance journey time reliability by upgrading the existing A1 to dual 3-lane motorway standard. Works began in March 2009 and the contractors worked closely with design partner AECOM to deliver the project.

An enormous amount of carriageway construction was involved in the scheme – including 2.5Mt of earthworks, 1Mt of imported starter and capping layers, and 980,000t of sub-base and asphalt.

Speaking during the course of the project, JV Project Director, Chris Hayton, commented:

“Logistics are a challenge on this project given the sheer volume of deliveries and the need to manage them safely. We have 700 people working out here. Safety is our number one priority.

“Nobody is allowed to cross the A1 and we have 250,000 wagon loads on and off site to manage. When divided by the number of working days we have, it works out that we have to handle on average 60 vehicles an hour. It’s a massive issue because we cannot have vehicles queuing to discharge and backing up access points.”

The A1 Dishforth to Leeming project made the best possible use of ‘site-won’ materials to minimise the import of first generation stone. In order to minimise the carbon footprint, stone was sourced locally and balanced out amongst local quarries to minimise the impact of wagon journeys on the local population along the delivery routes.

Furthermore, works traffic was banned from using many of the local roads and great effort was made to inform the public in advance of any proposals. Working hours were restricted where possible to 07:00 – 19:00 Monday to Friday, and neighbours were offered alternative accommodation if necessary.

Working with care

The road passes through a Scheduled Ancient Monuments (SAM), site where considerable archaeological findings were discovered during investigation and recording by a team of 35 archaeologists.

Considerable efforts were made to protect various animal species – badgers, otters, bats, great crested newts and nesting birds – and the site team also had to deal with a number of noxious or invasive plants such as giant hogweed, Japanese knotweed, Himalayan balsam and ragwort.

Chris Hayton commented:

“The drainage from the existing A1 issued directly to local watercourses. With the new scheme, all the water from the new road flows to balancing ponds, which attenuate the flow to watercourses and carry out initial settlement of solids as well as some treatment of pollutants through the action of reed beds.”