The previously derelict Stamford House in Altrincham is being given a £5 million facelift, thanks to property developers Petros.
The grade two listed building is being converted into 24 two bed apartments on the first second and third floors; with the ground floor comprising of nine retail units.
Speaking to Premier Construction Peter Holden, Construction Director, from CKC D & B Ltd told us about the works taking place on site, which is situated on the junction of Stamford New Road and Moss Lane. Main contractors CKC D & B Ltd began the project in July 2012 and hope to have completed the development in July 2014. Peter said:
“When we first got possession of the Stamford House site it was derelict, apart from one retail unit that was still trading; although that had a lot of water ingress coming through the ceiling. The retailers moved out after 3 months of us being on site.
“We have completely refurbished the buildings shell, stripping the roof completely, reroofing the block and refurbishing the 300 + original feature timber sash windows. There has been an extensive timber repair process because we found a lot of dry rot and wet rot; so we have had a dry rot specialist on site to ensure complete eradication.
“We have also renewed a lot of the floors; re-pointed about 80% of the building masonry; replaced a lot of the steel frame in the fabric of the building which was corroded and causing substantial cracking. Split and fractured redbrick and clay terracotta blockwork has also been specially remade.”
The first phase of the project involved ensuring the building was completely wind and water tight. The retail units on the ground floor have been completely refurbished with new shop fronts and internal redecoration.
The second phase, of which the construction team are 40% through, involves converting floors one, two and three into 24 apartments. Work is currently occurring in the first wing, comprised of 12 apartments. Four of the flats have the kitchens installed and soon mechanical works will begin before the final decoration is completed.
As the building is listed the entrance and core area of the property has been maintained in its original style, with the original timber panelling being retained. There is a contrast between the properties traditional main areas and the apartments which are contemporary, modern and decorated in neutral shades. Manchester based Architects, Hulme Upright, are involved in the interior design and architectural aspects of the project; with Stewart and Harris being the Structural Engineers.
The team will then move onto phase 3 and work on the remaining 12 apartments. Phase four, which is in the planning stages currently, will involve the demolition of Atlanta Chambers; a building based in Stamford House’s courtyard. The ground floor will become a retail unit; the floors above will also house similar two bedroom flats. The building fronts onto the tram, train and bus interchange which is currently being refurbished.
Owners Petros, a property development and investment company, will let the retail units and apartments upon completion of the project. Petros has owned Stamford House for 30 years or so; previously the building contained retail units and office facilities. Due to there being no demand for offices in the area the decision to change the property into rentable property was taken. With excellent transport links for commuters travelling to Manchester the residential and retail property is ideally placed.
Kierson Ltd
Kierson Ltd specialise in the restoration and upgrading of original timber windows. The company also manufactures sash windows for the heritage market.
The company client base is wide reaching, encompassing country estates and Grade I listed properties, to commercial properties and individual private houses. Among other projects Kierson are involved in repairing and replacing windows for Nottinghamshire County Council at a variety of local schools. The company can deal with one window to 400 depending on the size of the project; either refurbishing or replacing windows.
Managing Director Alison de Roeck said Kierson are very pleased to currently be working alongside CKC restoring Stamford House. Alison added:
“It is a pleasure to see this beautiful building restored to its former glory. We were on site for a year and our part of the project is now completed.
“We pride ourselves on our customer service; tailoring each job to the individual requirements of the building and client. We do our utmost to restore heritage properties to how they would have been originally.