London & South East

London’s deepest tunnel

Lee Tunnel, Abbey Mills Pumping Station, London, Stratford

A £635 million tunnel is being constructed to tackle discharges from London’s largest Combined Sewer Overflow system at Abbey Mills Pumping Station in Stratford.

The tunnel will stretch for four miles from Abbey Mills to Beckton in Newham and will address 40% of the total discharge in the city.

It will prevent more than 16 million tonnes of sewage mixed with rainwater overflowing into the River Lee each year. The tunnel will capture the sewage and transfer it to Beckton Sewage Treatment Works, which is being expanded by 60% to enable it to deal with the increased volumes.

The Lee Tunnel Project is part of a three phased programme aimed at cleaning up the River Thames from the discharge of untreated sewage. Currently sewage is discharged whenever there is rainfall and the existing sewage system is overloaded.

The Lee Tunnel is the first of two tunnels, which will collectively capture an average of 39 million tonnes of sewage a year from the 35 most polluting combined sewer overflows (CSOs), built by the Victorians as part of a sewerage network that still serves London 150 years on.

In January 2010, Thames Water awarded the main contract to design and construct the Lee Tunnel to the MVB joint venture. MVB is a group of three major engineering companies. These include Morgan Sindall PLC, VINCI Construction Grands Projects SAS and Bachy Soletanche Limited.

MVB has appointed three organisations to provide design services including Mott MacDonald Limited, Underground Professional Services and Bachy Soletanche Ltd. These companies took charge of shafts civil engineering, hydraulic engineering, and mechanical, electrical, instrumentation controls (MEICA) engineering, tunnels and surface structures engineering, and shafts diaphragm walls engineering.

Lee Tunnel, Abbey Mills Pumping Station, London, Stratford

Roger Mitchell, Deputy Project Manager, said the project is the largest contract ever let in the UK water industry. Speaking to Premier Construction Roger added:

“Work began in September 2010 and we aim to be completed by the 31st December 2015. The tunnel will be 6.9 kilometres upon completion and as of today we have constructed 5.287 kilometres of the structure. So we are 76% completed.

“It is a hugely important job for the water industry. I’m very proud to be associated with it; I was here before the start of the contract and I hope to be here at the end.”

The tunnel is London’s deepest-ever. The team have tunnelled under high groundwater pressures and passed through four miles of abrasive ground and erected four out of five of the tunnels shafts.

The 80-metre-deep shaft at Beckton sewage works is where tunneling work began. A 120-metre-long tunnel boring machine, named Busy Lizzie by a local primary school for good luck, is being used to construct the seven-metre-diameter tunnel – the width of three London buses.

The team lowered Busy Lizzie 80 metres into the ground in 2011 and began tunnelling in early 2012. The machine has been custom-built to suit the ground conditions, which are mainly chalk with highly abrasive flint.

Busy Lizzie is a ‘slurry closed faced’ tunnel boring machine. It will blend over 100 tonnes of excavated chalk with water for every one metre of tunnel advance, forming a white slurry – a similar consistency to single cream, before transporting it through a pipe the length of the tunnel, so it can be processed above ground. Tunnelling work began in January 2012, progressing at a rate of 17 metres a day. Tunnelling is expected to finish in late 2013.

The tunnel will be double lined; the first lining is a segmental concrete lining which is installed as the development proceeds. A further concrete lining will be installed when the whole tunnel has been constructed.

Lee Tunnel, Abbey Mills Pumping Station, London, Stratford

SAMT 

Founded in 1988, SAMT is a French Group specializing in the design, manufacture and fixing of concrete reinforcement and mechanical couplers for reinforcing bars. Well known by all major French civil contractors, SAMT has participated in the construction of prestigious buildings such as the Millau Viaduct where all the activities of the group were involved, along with nuclear power stations in France and China, and military installations.

Having already worked in a few different countries together with French companies, SAMT is now present in the UK working on both engineering and coupler activities in association with Byrne Bros.

On the Lee Tunnel project, SAMT Ingénierie has been involved in the design of the concrete reinforcement of Beckton, Abbey Mills and connection shafts in accordance with the techniques chosen by MVB. A site installation was also drawn for Abbey Mills pumping station.

Frédéric Thirion, CEO of SAMT, said:

“As usual at SAMT, the high technical level was a motivation to engage our taskforce on the Lee Tunnel project. Even though the concrete reinforcement fixing was not our target here, we made it our goal that companies performing this work would not encounter difficulties whether in reinforcement fixing or in concreting.”

About the author

Roma Publications