IJmuiden Sea Lock

IJmuiden
Written by Roma Publications

IJmuiden Sea Lock

A new large sea lock is being constructed at the entrance of the North Sea Canal at IJmuiden that will provide access to the Amsterdam port region. The new lock will be 500 metres long, 70 metres wide and 18 metres deep, making it the world’s largest sea lock. Construction began in January 2016 with the new lock available for shipping in early 2022. From then on, the port of Amsterdam will be accessible 24 hours a day.

The North Lock at IJmuiden will reach the end of its technical service life in 2029 and has become too small for today’s ever-larger seagoing vessels. A new large sea lock allows new-generation larger vessels to pass through the North Sea Canal smoothly and safely and with a larger lock, the port has the possibility to grow from today’s 90 million tons to 125 million tons of goods handled per year.

Premier Construction magazine spoke to Jan Rienstra, Stakeholder Manager from Rijkswaterstaat about the project.

What does this project encompass exactly?
“For this project, the Dutch Ministry of Infrastructure and Water Management, its executive body, Rijkswaterstaat, the province of North-Holland, the city of Amsterdam and the Port of Amsterdam joined forces with the municipality of Velsen to make this new sea lock possible. The project is partly financed by the CEF-programme, formerly known as TEN-T, of the European Union.

“The new sea lock is being built by consortium OpenIJ, as commissioned by Rijkswaterstaat, because the current sea lock (Noordersluis, 1929) needs to be replaced. The new sea lock will be larger and constructed ten years earlier, due to an increase in vessel sizes. The enlargement of the sea lock will improve the accessibility of the ports and industries along the North Sea Canal, allowing vessels to pass tide independently, smoothly and safely.”

Is work on the new lock being phased? If so, where are you currently up to?
“The design stage is almost finished with the building phase currently underway.”

What is the biggest challenge of the project?
“The stability of the existing locks has been a challenge while building a very large lock nearby. Whilst work is underway, transport and ships continues through the existing locks.”

Once completed, what will this project mean for the people using it?
“Once completed, this project will offer a special lock, in a special spot. Rijkswaterstaat operates to ensure that the Dutch inhabitants have protection against flooding, sufficient clean water, smooth and safe transport by road and water, reliable and useful information and a sustainable living environment and that is something that the new sea lock will provide.”

How important is if for you to be involved with this project?
“We are very proud to be involved with this project.  As part of this project, Rijkswaterstaat is fulfilling three social roles: a public-oriented network manager, a leading project manager and an effective crisis manager.”

For more information about the New Sea Lock, visit: https://www.portofamsterdam.com/en/port-amsterdam/new-large-sea-lock