Guernsey Electricity

Guernsey Electricity
Written by Roma Publications

Guernsey Electricity

Guernsey Electricity is working to upgrade key infrastructure in St Peter Port as part of its long-term plan for continuous re-investment in the Island’s electricity network.

Two 20 MVA (Megavolt amperes) transformers, have been installed on land east of Beau Sejour Leisure Centre and will supply around 25% of the Island’s electricity and the majority of the Island’s capital, St Peter Port. The equipment will improve resilience in this local network and provide enhanced capacity to meet a more electric future.

Jon Sexton, Head of Engineering and Design at Guernsey Electricity, said: “The new equipment supplies around a third of our customers. This installation forms an important part of the continual investment in our existing infrastructure. It will future proof our local electricity network, provide extra resilience along with enhanced capacity to meet a more electric future and the switch from fossil fuels.”

The transformers which each weigh 29 tonnes, arrived in Guernsey from the UK in September and were transported to site on innovative self-propelled, remote-controlled vehicles travelling at 4mph, by a team of operators walking alongside.

Stephen Rea, Project Manager, at Guernsey Electricity said: “The transformers were built in Romania and were brought across Europe. They arrived by boat in Guernsey and the 2.5-mile trip was conducted using a SPMT, a remote-controlled vehicle, following a carefully planned route of the most accessible roads. Effectively it was a very qualified driver operating the vehicle using a remote control. They were driven and accompanied along Guernsey’s seafront then inland to the substation.”

Jon added: “As a company, the need to consider and protect our environment forms a key part of any investment decision. For this project, the planting of native trees and plants, as well as installing birdboxes and bat boxes will aim to increase the biodiversity to the local area and improve habitats for existing wildlife.”

The Guernsey Electricity team has worked with Environment Guernsey to identify initiatives to support existing wildlife and encourage biodiversity to the surrounding area.

Stephen added: “This is a major project for our company. It is a significant investment in the Island’s infrastructure and is preparing the Island for the energy transition and increasing the switch to electricity and renewables. It is key delivery of new, major infrastructure, delivered in a tight location.”