Queens Pier restoration, Ramsay
The restoration of an iconic Isle of Man landmark is forging ahead with the second phase of works to refurbish bays at the historic Queens Pier in Ramsay now making progress.
The project is being carried out by the Queen’s Pier Restoration Trust, who signed a five-year lease with the government in July 2017 to refurbish bays 1 – 3 of the Victorian landmark.
Following on from the first phase, the second phase involves similar works on a further five bays. There are 60 bays in total and eventually all the ironwork along the length of the pier will have to be replaced.
This community restoration project, led by Captain Stuart McKenzie since 2017, was originally founded by Tom Durrant in 2016. Dennis Curphey has taken over as project manager for the second phase, as Stuart is concentrating on his role as chairman of the Queens Pier Restoration Trust.
Measuring 2,160ft long, the pier was built for the Isle of Man Harbour Board as a low water landing stage. Construction began in 1882 and the pier was officially opened on 22nd July 1886.
The pier was finally closed in June 1990 after a massive fall in numbers of people using it and increasing maintenance costs. Some of the main timbers and under-deck girders were badly rotted, and a complete overhaul was necessary. The Isle of Man government deliberated on repair options and costs, but nothing was done for 25 years – until the Queen’s Pier Restoration Trust was set up.
According to the Queen’s Pier Blog Manx Transport Review – Spring 2022: “We had a turbulent time at the pier with Covid-19 shutting us down and delaying the completion of Phase 1. That said, we did manage to complete this phase one year earlier than required by Government. The completed first phase looks very grand and was appreciated during the summer of 2021 by members of the public being invited to visit the pier each Sunday afternoon, no doubt attracted by the old train and passenger carriage on display, which will run along the pier again.”
Phase one was opened by retiring Lieutenant Governor, Sir Richard Gozney on 22nd July 2021, which was followed by members of the public stepping foot on the pier for the first time in 30 years.
A revised lease to refurbish the five further bays in Phase 2 was signed the following week.
So far, the first bay measuring 40 ft x 40 ft has been by far the most difficult to restore, because it is larger than the other bays as it is attached to the promenade. A further complication was that the pier abuts the promenade at an approximately 20-degree angle rather than at 90 degrees, so all the girders and wooden beams which needed to be refurbished at the promenade end had to be shaped to accommodate this.
Works to bay 1 involved replacing all of the cast iron girders with mild steel, fabricated at Gallas foundry in Douglas. This was then galvanised on Merseyside and painted with five coats of marine epoxy by the volunteers, on its return to the island.
New cross larch timber beams and longitudinal stringers laid on top of the girders were sourced from the Isle of Man with the assistance of the island’s Forestry Department.
The decking surface of the pier, made of Ekki timber sourced from West Africa, was then laid on top of the longitudinal stringers.
In conclusion, the Queen’s Pier Blog Manx Transport Review commented: “As with everything the restoration needs money and we have been fortunate in getting a £30K legacy from Mr Jonny Green, which paid for the steel on Bay 3. This was followed by a donation of £50K from the Manx Lottery Trust which will pay for the greater majority of Bay 4. Finally, we very recently received a substantial legacy which will pay for the majority of another 2 bays on Phase 2. These legacies and donations enable us to continue with the restoration, but with prices soaring almost weekly, we can only estimate how far our funds will stretch. We are currently awaiting the fabrication of the steel for Bays 4 and 5 and we hope to have these two bays finished by late summer 2022.”