Marina Park Phase 1

Marina Park
Written by Roma Publications

Marina Park Phase 1

Marina Park is a public open space in the South Docklands Cork and is seen as a key economic driver and catalyst for the regeneration of the South Docklands area. This project, which has been shortlisted in the 2002 Irish Construction Excellence (ICE) Awards, is the first phase to be constructed and represents approximately 6 hectares of the total 32 hectares park site. As well as Marina Park, the site contains several protected structures, including the 1760’s Navigation Wall, Páirc Uí Chaoimh stadium, and the Atlantic Pond. As a finalist in the 2022 Irish Construction Excellence Awards in the Civil Engineering Under €10m category, the new Marina Park design is based on a series of themes: activity, accessibility, ecology, and culture.

Marina Park Phase 1, delivered by Sorensen Civil Engineering Ltd., contains some unique features representing the ingenuity of the design and the skill in construction. Most notably is the use of polished concrete as a surface finish to some 6,200sq.m pedestrianised public realm in addition to the riverfront walkways and seating areas. This is a move away from the more normalised paved finishes providing a product and finish which is not only cost-effective and durable but sustainable as the material is sourced locally. The provision of a specialist jetted water feature and a cover structure for use as a Central Plaza. The nature of the existing environment as an industrial basis had resulted in contamination of the existing soil structure requiring the management of some 15,000 cubic metres of contaminated material.

The project was in development for several years before coming to tender in November 2019 with contract award and works commencement dates in March 2020. Originally planned with a construction period of 12 months, due to the Covid 19 Pandemic, the timeframe was extended by 8 months with substantial completion being issued in July 2021.
Tender at approximately €6.5million and an outturn cost of €7.0million, the project was completed within the scope of the original budget while considering variations issued at the direction of the Client and because of the impact Covid 19 on programme and work practices.

The brief provided to Sorensen required the completion of the first phase of Marina Park, the works included clearing the site, construction of the 6,200sq.m public realm space, two bridge structures and various culverts, the construction of the Central Plaza meeting place, the design and installation of a bespoke jetted water feature, together with the extensive planting and landscaping requirement.

Key project outcomes:

The project was started at the commencement of the Covid-19 Pandemic resulting in two significant periods of suspension. Despite the difficulties, the project was managed through a process of cooperation and partnership and was largely completed on time and within the budget. This allowed the adoption of some key value engineering approaches which limited the financial risk to both the Client and Contractor.

Acknowledging the extensive contaminated material on-site and the need to export the material to an off-site landfill facility, the Sorensen team worked on a plan to maintain the material on site. As the material provided no risk to human health it could be utilised as engineered fill under the future paved areas. This provided a more sustainable solution reducing the need for imported fill, removing the risk of transportation, and maintaining the material within its point of origin. This method of sustainable construction combined with others utilised throughout the project generated a green saving of 1,425,387.24 kg CO2eq which is the equivalent greenhouse gas emissions generated from using 18.9 tanker trucks worth of petrol or burning 7.9 railcars worth of coal or consuming 3,300 barrels of oil.

Marina Park