The Youghal Eco-Boardwalk Phase 2 comprises the construction of a new ‘Eco Boardwalk’ on the seaward side of the Ballyvergan Dunes from Claycastle to Redbarn, Youghal, Co. Cork. The £1.5 million development is Phase 2 of the Eco Boardwalk project and entails the erection of an approximately 1.1km stretch of 2,300mm wide elevated composite structural steel/timber decking boardwalk and ancillary works along the beach from the Claycastle car park to the Quality Hotel at Redbarn. Works were carried out in an environmentally sensitive environment. This sustainable timber designed boardwalk now forms part of the longest seafront boardwalk in Ireland and is a finalist in the 2022 Irish Construction Excellence Awards in the Leisure or Tourism Under €10m category.

All of the works were carried out in a marine/tidal environment. The design focussed on sustainable materials, products and methodologies yet it was suitably robust to withstand the constant attack from the adjacent sea.

Project’s Programme

The project was in development for several years before coming to tender in February 2020 with an award in May 2020 and the commencement of work in June 2020. Originally planned with a construction period of 7 months, the timeframe was extended by 6 months because of the Covid 19 Pandemic with substantial completion being issued in early June 2021.

The Client’s requirements

The brief required the completion of the 1.1km Eco Boardwalk, the works included clearing the site, initial SI and installation of 6no. test piles, installation of 1,000no. 220mm diameter x 9.5m long CHS driven piles, construction of steel substructure, timber decking, timber steps, in-situ RC steps, footpaths, construction of an RC marine slipway, fencing, supply and installation of changing huts and public seating, installation of 2no. bike stands, installation of rock armour and reprofiling of the beach along the boardwalk.

Key project outcomes and metrics

The project was started at the commencement of the Covid-19 Pandemic resulting in two significant periods of suspension. Despite this setback, the project was largely completed on time and within the budget. Despite the difficulties, the project was managed through a process of cooperation and partnership. Given procurement time constraints, the client could not complete sufficient SI pretender. Sorensen collaborated with the design team to carry out a series of test piles to establish the depth of competent rock. Once the test piles were complete, Sorensen carried out Static Tension Tests on the piles to calculate the pile displacement in mm under upward loading. Dynamic Tests were also carried out on the trial piles to determine the ultimate bearing capacity of the piles. This process provided our client with great comfort in the suitability of their design. In further collaboration, Sorensen postponed the procurement of the 1,000 CHS piles from the UK until the tests were complete and the specification of the piles could be confirmed.

Outline any innovative use of materials or products

Sorensen proposed an alternative rare specialist hardwood called Lophira alata known as Ekki for the boardwalk decking. This material was sourced in Cameroon, West Africa and is known locally as ‘Red Ironwood’. Ekki is amongst the hardest and most dense timber in the world. The maintenance requirements for the Ekki material are significantly lower than alternative hard woods given its hard-wearing and durability characteristics. It provides for an exceptionally high-quality and robust finish to the boardwalk. The Ekki timber used for the boardwalk was sourced from a sustainable forest whereby only mature trees are felled once they have reached the carbon intake capacity. New trees are planted, and the sustainable process starts again. These timber elements will continue to store carbon in their new surroundings along the Youghal Eco Boardwalk for many years to come.