During this project, P&D Lydon constructed a cycling and walking amenity, providing connectivity between Castletroy College and Castletroy Gaelscoil, linking Castletroy College Road to the R445 Dublin Road in a north-south direction. This was with the aid of Limerick City and County Council architect and MHL Consultant Engineers. This project has been shortlisted in the 2022 ICE Awards in the Civil Engineering Under €10 million category.

The works consisted of a new 3.5m wide cycleway alongside a new 2.5m wide footpath, with grass verges on both sides. The main spine extends for approximately 820m linking Castletroy College Road with the access road to the Gaelscoil. Secondary spines link to the residential development to the east (Castlebrook) (approximately 175m in length) and Castletroy Shopping Centre (Town Centre) to the west (approximately 285m). The works also included the installation of LED public lighting, a CCTV system provision, security fencing where appropriate, tree and shrub planting areas as well as a surface water drainage system and culverting of a section of an open drain.

Works started on the project in January 2021 and were completed ahead of schedule in September 2021. The final cost for the construction of the project was around €1.7 million and has been positively received by the locals who are delighted as it has made it safer for children to walk/cycle to school.

P&D Lydon used a new innovative way to lay the 1.3km of 2.5m wide footpath using a machine which could lay up to 200m of footpath a day, as opposed to the traditional method of shuttering and hand pouring which would have only achieved 50m per day.

During construction, there were several key challenges, such as poor ground conditions and the impact the work would have on the local schools and community. In order to mitigate these challenges, P&D Lydon undertook detailed ground investigations, continuous monitoring and CBR testing in real-time during the construction process. All ground investigation and testing results were then correlated with the relevant Building Specs.

To reduce the impact on pupils and staff at both schools; P&D Lydon organised a detailed work plan during the initial stages to complete critical works during holidays in the school calendar. This was important as the overall programme and works flow needed to be also maintained to meet critical paths on the overall programme.

Regular meetings were held with the school representatives as the works progress where the impact and further mitigation measures were discussed. It was a main objective to build and maintain strong relationships with any impacted parties in order to reduce the impact of our projects on the community.

P&D Lydon Ltd is a family owned business and one of Ireland’s most progressive civil engineering contractors offering modern, efficient, and environmentally friendly solutions to their client’s needs. The company works with many of Ireland’s main utility providers, ESB, Irish Water and Irish Rail as well as many local authorities; including on this recent Castletroy Urban Greenway project in which P&D Lydon worked with Limerick City and County Council.