Work has now completed on the National Open Water Swimming Centre of Excellence by Sea Lanes Brighton. Work on the site began in August 2022 with the new centre opening to members and on a pay-per swim basis from 2nd June 2023.

For the development, Brighton and Hove City Council (BHCC) were seeking to continue the regeneration of the seafront by requesting expressions of interest for the redevelopment of the high-profile leisure site formally known as The Peter Pan Leisure Park.

Sea Lanes was chosen for its potential to bring Madeira Drive back into the spotlight by delivering a permanent 50m open air heated swimming pool, to increase the number of visitors and fulfil wider regeneration plans.

Formed by a passionate group of Brighton-based businesses and open water swimming enthusiasts, Sea Lanes Brighton is centred on physical wellbeing and environmental sustainability. The design of the scheme also respects the adjacent Grade II Madeira Terraces.

At the heart of the scheme is a 50m, six lane accessible swimming pool providing much needed swimming facilities in Brighton, as well as acting as a gateway for those looking to gain confidence in the sea, a training hub, triathlon, sea safety and lifeguard courses.

To ensure the facility is commercially viable and sustainable, the scheme offers a range of 23 carbon neutral modular business units providing flexible space for local, independent businesses offering retail, health and fitness and office space. These are supported by a food court with street food kiosks and seating areas.

The site, located next to Madeira Terrace, is very sensitive. Planning approval was granted in March 2021 after overcoming scrutiny from BHCC planning department, heritage groups and residents, on the design of the development. Initially proposed as being bright and colourful, the site has now been softened to compliment Madeira Terrace’s appearance. The challenge of building on the previously developed site was also significant. The existing concrete slabs had to be carefully removed with minimal vibration so as not to cause damage to the cast iron Madeira Terrace structures.

The height of the building has been reduced by 1.27m to lessen its impact and the business units have been orientated so each one has sea views and glass balustrading to afford uninterrupted views of the sea from Madeira Drive. Green roofs have also been introduced to increase the ecology in the area as well as reducing surface water run-off.

Sea Lanes also incorporates extensive energy monitoring to build a data base of energy and water consumption over time.  This will be used to monitor and analyse its effectiveness and carry out refinements, to further reduce operational energy consumption. To meet the very high peak heating loads during the winter, high-efficiency gas fired condensing boilers together with a contribution from solar-thermal panels are also being used and future proofed to ensure that the heating plant is compatible with a switch from natural gas to hydrogen in line with emerging Government policy.

From an initial planning application in 2018, to opening in Spring 2023 Sea Lanes has adapted the design to meet the needs of the community, its heritage and environment whilst restoring a derelict site using the latest building technology and insight.

 