Beau Sports and Activities Centre, Beaulieu Convent School, Jersey
Hailed a success by pupils and teachers alike, Beaulieu Convent School’s impressive brand new state of the art Beau Sports and Activities centre was recently opened by former England Roses Netball Captain, Serena Guthrie MBE.
A Roman Catholic independent school for girls in St Helier, Beaulieu, which educates both primary and secondary age pupils, was established in 1951 by sisters from the Order of the Immaculate Conception.
The new centre, for primary school pupils, was constructed on a sloping site on land previously occupied by a private access road to the school. This road was re-routed both to make way for the new building and to provide more efficient access to the school.
Project architects were Page Architects; main contractors were AC Mauger.
The building was constructed as a large extension to Beaulieu’s primary school, to which it is connected via a new first floor link corridor. This was the architects’ design solution due to the sloping nature of the site.
George de Sousa of Paige Architects commented: “We have a long standing relationship with the school over 15 years and have carried out quite a few projects for them – which is why we were invited to take on this development.
“The school’s former sports hall was very small, and a survey conducted by the school revealed that parents of pupils felt that a new sports hall was the top priority that was needed.”
The new centre is on two levels with the ground floor incorporating two sets of changing rooms, a PE classroom, offices, fitness centre, dance studio, storage areas and plant rooms, and the first floor comprising the national court-sized sports hall and the link corridor. Gara sports flooring has been used on both levels and sound insulation has been installed on the upper level.
The flat roofed building is structured around a concrete frame at ground floor level, with a steel frame above. The whole of the west external elevation is glazed in a Sarpa system to maximise light into the building, with the remaining elevations in rockwool insulated render, with high level windows to allow for natural cross ventilation. The insulation will enable the building to retain heat in the winter, whilst remaining cool in the summer.
External works included the laying of footpaths, some tree planting, and the creation of a small contemplation area with two benches.
Apart from the sloping site, another challenge of the project was delays in materials delivery in the immediate post-Covid period.
George de Sousa commented: “This was a successful project and turned out really well. The team did a very good job and feedback from the teachers and pupils has been excellent. In addition, the centre has also become a good community facility for Jersey, with the school renting out space to local groups out of hours.
“This was an important project for us and was the largest sports facility we have ever worked on.”