Completed in 2021, an incredible conservation project to repair and protect the precious medieval hammer beam roof and gothic roof lantern of Westminster Hall has been shortlisted for a 2023 Wood Award.

Originally constructed in 1097, Westminster Hall has a long, rich history. It was remodelled in the late 14th century with the addition of a hammerbeam roof, complete with timber arches, trusses, purlins, rafters and timber sarking, and weighing 660 tonnes in total. Today, it is one the most revered, Grade I listed, World Heritage Site buildings in the country.

In 2003, the decision was made for Westminster Hall to become the main entrance for those visiting Parliament. Major works were completed between 2006 and 2008 to rebuild steps that had been sinking. In a later phase of the works the North wall was cleaned and repaired, and the Jubilee Window was installed in 2013; the remaining three walls were cleaned and repaired over the course of 2014-15. Following the completion of these works, attention shifted to the 92-foot-high roof.

For architect, Donald Insall Associates, the focus of the project lay in conserving the hall and improving its suitability as Parliament’s visitor entrance. Achieving this saw the project divided into four stages of works, three of which have now been completed. Also working on the project were Dolmen Conservation & Joinery – specialist carpentry and joinery sub-contractors – and Adam Watrobski – Principal Architect for the Houses of Parliament.

Adam was responsible for the project’s oversight, briefing, and quality control. Speaking with PREMIER CONSTRUCTION, he said he loved getting to work hands on with the roof: “One of the standout elements of the project for me was actually being up there and experiencing the roof itself. It’s fascinating, to have gotten timbers of that size in place at the end of the 14th Century is a monumental achievement.”

A strong focus on traditional repair techniques characterised much of the project, with the roof’s trusses being restored with conservation carpentry using traditional repair techniques, to ensure reversible repairs. Damaged timber at the Hall’s south-eastern end was a significant point of attention – the damage being the result of Second World War bombings. Repairs were also needed in the north-west area of the roof, which was damaged in an IRA bomb in 1974, and these were completed alongside smaller repairs throughout to address where the roof had crumbled. Much of the roof was also cleaned to scrub away the dirt that had accumulated over the years.

A series of repairs were also made to the roof’s lead-clad lantern. Three storeys high, the lantern was damaged during the Second World War and rebuilt during the early 1950s as well as possible, given the post-war economy and the continuing lack of materials. Recent works saw the lantern stripped down and rebuilt, as well as facilitating easier access and effective drainage. Adam commented: “It was a great thrill to get it unblocked from below and working – you can now actually see into it and the light coming from above into the hall.”

Currently, works are being completed with respect to the roof’s new lighting, improving visibility throughout the hall and of the roof itself. The existing lighting was fitted by Sir Frank Baines who repaired the roof between 1914 and 1923. Just as Baines was about to leave the Hall, he stopped and decided to install low-hanging chandeliers. Today, these chandeliers make it difficult for visitors to see the roof properly, and so the final stage of the project will set about replacing them.

Reflecting on the project, Adam addressed some of the unique obstacles that it posed: “One of the main challenges when doing works in Parliament is that we have to keep Parliament running. Nothing can interfere with the work of both houses of Parliament. We have a large Visitor Department and regularly offer tours to schools, visitors and Members’ constituents; we had to make sure that we could keep these going too. In order to do this we had to complete the works at night on scaffolding suspended in the roof.”

Given the project’s incredible attention to detail, it’s no surprise that Westminster Hall Roof and Lantern has been shortlisted in the ‘Buildings’ category at the 2023 Wood Awards. The original roof was built in 1395 from English Oak sourced from Royal forests, and all the repairs have been made using the same type and quality of wood.

For Adam, this nomination “reflects the excellent work by Donald Insall Associates, who have a very precise approach to things and a huge ability to accommodate the unexpected. Above all, it is also a testament to the craftspeople who carried out the work, which is the bit that we all see. I’m absolutely delighted to have been a part of it.”

For Jack Massey, Director of Dolmen Conservation & Joinery, the project was a once in a lifetime opportunity: “We all felt a real responsibility to ensure the building was returned to a condition that future generations could enjoy as we have.”