Derrinlough Wind Farm

Derrinlough
Written by Roma Publications

Derrinlough Wind Farm


Located on Clongawny and Drinagh bogs located in Co.Offaly, Derrinlough Wind Farm is being developed by Bord na Móna. Consisting of 21 turbines, the wind farm will have a maximum export capacity of 105 Megawatts.

Being completed by BAM Civil, H&MV Engineering and Jennings O’Donovan & Partners, the wind farm will generate renewable electricity for the domestic electricity market in Ireland and will make a significant contribution to the achievement of Ireland’s 80% renewable electricity target by 2030.

Speaking to PREMIER CONSTRUCTON MAGAZINE, a spokesperson for H&MV Engineering said: “The innovation implemented in the construction of the Derrinlough Wind Farm project involves transforming the existing industrial peatland into a multifaceted post-use area, incorporating both large-scale renewable energy generation and advanced rehabilitation of the surrounding bog environment.”

Given the specific location of the Drinagh Bog, the H&MV Engineering design team meticulously factored in the existing drainage infrastructure, a consideration that garnered praise from Bord na Móna.

H&MV Engineering said: “Working within a recently retired industrial peatland has presented challenges with dewatering deep excavations and managing water through the existing bog drainage.

Peatland rehabilitation was also being progressed throughout the project presenting a unique challenge as this was the first time construction for green energy generation and peatland rehabilitation happened simultaneously.”

The 21 turbines of the wind farm will have an overall blade tip height of up to 185 metres and within this size, various configurations of hub height and rotor diameter may be used. Due for completion in August 2024, the wind farm will see approximately 6.5km of local amenity links provided. This will include three access points from the adjacent road network and provision for future connectivity to Lough Boora Discovery Park and the proposed Whigsborough Amenity Walk.

Construction on site commenced in February 2023 and recent completed works include the first pre-installation of the base and mid one tower section of Turbine 6.

As part of the project, Derrinlough Wind Farm has launched a Construction Community Benefit Fund (“The Fund”) to facilitate the support of local communities during the construction phase of the project.  The Fund is open to local community-based project groups and voluntary organisations located within, or working with, communities in the vicinity of the development or turbine transport route.

Commenting on the project so far, H&MV Engineering said: “Bord na Móna has expressed satisfaction with the quality of the project and the innovative ideas and measures implemented on-site. As H&MV Engineering consistently collaborates with Bord na Móna on various wind farm endeavors, a strong rapport has been forged, grounded in principles of safety, work ethic, quality, and meticulous attention to detail.

“In the pursuit of achieving net-zero greenhouse gas emissions by 2045, the Derrinlough Wind Farm project prioritises both renewable energy and carbon sink development. A key objective involves advancing the rehabilitation of the peatland, with H&MV employing innovative Environmental, Social, and Governance (ESG) practices to safeguard the biodiversity of the bog and neighbouring wetlands. These practices include on-site awareness campaigns, mobile apps for reporting environmental issues, community outreach, and integrating ESG considerations into design decisions.”

For their work on the wind farm, H&MV Engineering has been selected as a finalist for the 2024 Irish Construction Excellence awards in the Innovation in Construction Category.