Tyne Bridge, Newcastle


A multi-million-pound project to restore Newcastle’s iconic Tyne Bridge to its former glory is making good progress.

The project, for Newcastle City Council and Gateshead Council, with the support of funding from the UK Government, commenced in April 2024, with Esh Construction as main contractors.

In August 2018, the bridge was Grade II* listed by Historic England for architectural and historical interest. The rating means that the bridge is listed as a structure of special interest and warrants every effort to preserve it. To adhere to the bridge’s listed status conditions, the construction work focuses on repairing the structure’s components, instead of replacing with new components.

The four-year project will see more than 1,000 steelwork repairs carried out, as well as grit blasting and re-painting, concrete repairs, drainage improvements, stonework and masonry repairs, bridge deck waterproofing and resurfacing, parapet protection and bridge joint replacement.

Currently, within the scaffolding adjacent to the Gateshead Tower, grit blasting has removed 96 years of previous paint coatings, and the steelwork has been cleaned, repaired where required, and repainted in its distinctive Hollybush green, which was first unveiled last October.

The final repairs and painting in this section are now being completed, with the scaffolding being completely removed in the Spring.

Work moved on to the Newcastle side last August, as scaffolding was erected under the arch adjacent to the Newcastle tower, in preparation for the restoration works.

As with the Gateshead works, the scaffold was fully encapsulated for teams to begin the mammoth task of cleaning, grit blasting and steelwork repairs before the final stages of painting can take place. Works adjacent to the Newcastle tower are scheduled to be completed by Autumn 2025, before moving on to the main bridge arch.

Following a re-sequencing to the planned works, installation of scaffolding commenced earlier than programmed to the underdeck of the main deck structure. Specialist scaffolders have been installing the temporary structure to the underside of the main carriageway across the Tyne between the two towers in readiness for critical works to the underdeck.

This work is followed by final boarding out and encapsulation to allow the team to grit blast, repair and paint the bridge deck soffit. Later in the year, work will begin on the main bridge arch with the installation of further scaffolding which will go ‘up and over’ from the underdeck. The ‘up and overs’ will see scaffolding installed around the curved plates on the sides of the bridge and over the existing parapet railing.

Operatives were working within the tight confines of the service void on the main bridge deck on the eastern footway. Several key sections of heavily corroded steel were replaced and major repairs undertaken to three of the deck hangers. 


This work has now switched to the western footway for the first quarter of this year, which saw a change in traffic management set up to accommodate the next phase of repairs.

Cllr Juna Sathian, cabinet member for Climate and Transport at Newcastle City Council said: “The restoration of our iconic Tyne Bridge is well underway, and it is great to see such progress being made.

“The scale of the work required is huge and, while there is still a long way to go before we see our iconic bridge standing proudly over the Tyne once again, it was wonderful to see the project get off to such a fantastic start in 2024. 

“2025 is shaping up to be another busy year on site, as restoration begins on the Newcastle quayside.”

Councillor John McElroy, cabinet member for the environment and transport at Gateshead Council, said: “Work is progressing well on the project and it’s great to see the contractors moving on to next phase of the bridge restoration.

“Recently, we have seen, up close, the difficult nature of the repairs for the team working on the bridge and they are doing a fantastic job in some challenging working conditions.”