Bagenalstown Wastewater Treatment Plant
Long known for its prosperous milling heritage, Bagenalstown is now set for a brighter future thanks to the recent upgrade of its wastewater treatment plant by Uisce Éireann (Irish Water), which was completed on programme and on budget.
John Sisk & Son (Holdings) Ltd carried out the upgrade works on behalf of Uisce Éireann under the supervision of Atkins Réalis engineers.
This major investment of almost €10 million by Uisce Éireann has more than doubled the plant’s treatment capacity, increasing from a population equivalent of 4,500 to 9,800. It has also substantially modernised and improved the wastewater treatment processes, leading to environmental and operational efficiencies.
This targeted investment by Uisce Éireann will ensure there is capacity available for future social and economic growth in the area, improved water quality in the River Barrow, as well as ensuring compliance with national and EU legislation.
Paul Fallon, Wastewater Portfolio Delivery Manager with Uisce Éireann, said: “This scheme was identified as a priority project needing an upgrade several years ago. The existing plant was built in 1995 and was significantly overloaded due to population growth.”
The works involved major improvements to the plant, including upgrading inlet works and storm holding tanks, and installing a new screened storm overflow chamber, sludge dewatering building, picket fence, thickener, administration building and control room.
Further works included: installing an aerobic reactor, air blowers, flow diversion chambers, pumps and distribution chambers, as well as upgrading the pumping station and carrying out all ancillary works including pipework, pumps, landscaping and associated site development.
In addition, electrical control and telemetry automation and control systems were upgraded to make work easier for the operator. The project also maximised use of existing structures wherever possible to gain maximum benefit from existing assets – for example an old tank was repurposed to provide storm storage. The upgraded scheme has a 10-year design horizon, with certain elements being 25 years.
Paul Fallon added that not only does the project allow the town to grow in terms of capacity for additional housing and business, but it also provides environmental benefits for the local River Barrow which has a lot of recreational users such as rowing clubs and fishing, as well as ramblers, and will ensure that the water treatment has no impact on the river and its ecology.
He concluded: “We are proud to have delivered this important project for the local community in Bagenalstown. These works now complete will allow the wastewater generated every day in local homes, schools and workplaces to be effectively treated to high standards and returned safely to the environment.
“We are satisfied that it was a success and demonstrates our commitment to the environment and to achieving our goals. It is great to add another project – completed on time and on budget – to our portfolio of schemes across the country.”
Cathaoirleach of Muinebheag Municipal District, Cllr Daniel Pender, said: “This project is a key milestone in improving wastewater services for the people of Bagenalstown and surrounding areas, and I want to thank Uisce Éireann for delivering this important work.
“Reliable infrastructure is critical to the future of towns like Bagenalstown, and this investment will bring lasting benefits to the local community.”
Uisce Éireann is responsible for the delivery of all public water and wastewater services in Ireland. They are committed to continuously upgrading and developing critical infrastructure to support the growth needed in housing and across the economy, while protecting the environment and safeguarding water supplies.