Ulidia Integrated College
An outstanding project to construct a new build 700 pupil school at Ulidia Integrated College campus in Carrickfergus, recently won its main contractors OHMG a place amongst the finalists in the prestigious Irish Construction Industry Awards 2025.
Shortlisted in the awards’ ‘Contractor Education Project of The Year’ category, the £25m NEC3 Develop & Build post-primary scheme is the latest addition to OHMG’s extensive portfolio of high-quality educational buildings, and has delivered an innovative, energy-efficient campus which significantly enhances the learning experience.
Carried out on a live, sloping campus, the project included phased demolition and new build, BREEAM Excellent design, BIM-led coordination, stakeholder engagement, and 910 trainee weeks. It sets a benchmark in safety, sustainability, innovation, and integrated education delivery.
Demand for pupil places has grown significantly since Ulidia Integrated College first opened in 1999, using largely temporary structures to accommodate an initial enrolment of 240 students.
The burgeoning Carrickfergus post-primary site was accordingly granted £25m by the Department of Education in the first tranche of Fresh Start Agreement funding for integrated education. Recognising its extensive experience in delivering high-quality educational buildings, OHMG was awarded the project for the school.
The Newry-based construction company was charged with delivering Hamilton Architects’ vision of enhancing students’ learning experience by building an innovative, energy-efficient campus maximising the site’s views over Belfast Lough.
Targeting BREEAM Excellent, sustainability was a major focus, while challenges included complex phasing of the build to avoid disruption to the operational existing school and surrounding neighbourhood.
Pre-construction work commenced in June 2021 with construction getting underway in September 2022. A first phase encompassing preparatory work and the new build was completed in November 2024, while a second phase – entailing demolition of the old school buildings and completion of the sports facilities was completed in March 2025.
The new school comprises 10,314 sqm of floorspace across two and three-storey buildings, housing classrooms, a library, learning resource centre, media facilities, sixth-form common room, technician accommodation and storage rooms. Also included are sports and multipurpose halls, toilet, cloak, shower and changing rooms for pupils and staff, general staff offices, a dining hall, kitchen and plant space.
With a drop of around 22m from the back to the front of the site, where the new build is constructed, extensive regrading was required to form levels areas for the buildings, car parking and playing fields.
Health & Safety Manager, Gavin Blaney developed a comprehensive traffic management plan to segregate vehicle and pedestrian routes, and scheduled deliveries to avoid peak traffic times.
Open lines of communication were maintained with the school throughout the project regarding any planned interruptions to services, while mitigation strategies included using quieter machinery to control noise and water spraying to suppress dust.
Priorities for OHMG included using sustainable materials, as well as solutions reducing labour and costs while accelerating the project timeline. Recycled aggregate was used for the haul roads, piling platforms and compound areas during construction. Lightweight concrete blocks decreased transportation and labour costs. Prefabricated structural concrete floor planks were craned into position to speed up installation time and reduce labour costs.
Use of cladding panels inside the roof parapet reduced on-site labour and accelerated the construction timeline. High-performance insulation materials including mineral wool slabs were used within the Kalzip roof build-up, enhancing acoustic properties and improving exam conditions in the sports hall.
Energy-efficient designs and technologies include LED lighting, HVAC systems and insulation, helped to generate long-term savings, with energy performance assessments including thermal modelling and airtightness testing conducted during the construction phase to verify compliance with the BREEAM Excellent target.
OHMG’s Construction Environmental Management Plan laid out anti-pollution, drainage management, water-quality monitoring and tree-protection measures, while its Buy Social Delivery Plan included 910 weeks of paid employment for apprentices.
Michael Houston, Principal of Ulidia Integrated College, said: “We are delighted with the instant, positive impact that the new building has had on learning and teaching – pupils and staff alike are very proud of their new school. Our previous building was for the most part temporary structures, and the new build has given our 730 pupils the proper facilities they needed and, very importantly for us, a permanent home for post-primary integrated education in Carrickfergus.
“OHMG supported and partnered with us throughout the entire build process and there is no doubt the building would not be same without them.”