Canal Walls and Chocolate Factory: Old Wharf renovated and regenerated

Canal Walls and Chocolate Factory: Old Wharf renovated and regenerated
Written by Amy

A former chocolate factory in West London next to the Grand Union Canal had been earmarked for regeneration. Though an attractive proposition for housing developers, the canal and the poor condition of the site’s wharf posed clear logistical challenges for any redevelopment works. With the wharf requiring repairs as part of the planning permissions to build apartments, national independent marine engineering and maintenance experts The Rothen Group was chosen to provide a practical solution.

Built in 1913 on the banks of the Grand Union Canal, the Hayes chocolate factory in West London had stood derelict since it4 closure in 2014. Formerly the first factory outside Switzerland to manufacture the iconic Milky Way chocolate bar, the site’s proximity to the capital made it ripe for regeneration. Seeing the site’s potential, developers Barratt London embarked on an urban renewal project in 2022 to deliver ‘Hayes Village’ – 1,500 new flats where the factory once stood, with over nine acres of green space, a light industrial commercial space, a 200m running track and a 1.3km trim trail.

Once so integral to import and export of goods for chocolate production, the canal posed a logistical challenge to Barratt London’s regeneration efforts. As part of the site’s planning permissions, the developer had agreed to open up 300m of canal footage to the public for the trail and community boat mooring. Yet the existing 60m wharf wall was in poor condition and needed to be made safe for boaters and residents alike on a very stringent 60-year life guarantee.

Continuous Complexities

Though the overall goal was clear, multiple local factors would make regenerating the former chocolate factory’s wharf more complex. Firstly, water restrictions meant any repairs would need to be carried out via land. Alongside this, as part of the project’s planning permissions, the canal renovations were scheduled to take place after the Hayes Village homes had been constructed, leading to further logistical challenges for marine engineering works.

Vibration from site activity also had to be kept to a minimum due to a nearby Network Rail bridge, and given the area’s former industrial use, contaminated materials would be dredged up during the project. As these waste products needed to be transported safely from the area for treatment and disposal, this added a further layer of complexity to the project.

With this need for expertise in mind, Barratt London looked to the specialist skills of The Rothen Group (TRG), first contacting the marine engineering company in November 2022. TRG’s remit was to design a practical solution within the limitations of the Hayes Village site to replace or renovate the existing wharf wall for community boat and recreational use. As part of this, TRG also had to liaise with the Canal & River Trust to gain the necessary permits and permissions required for any proposed works.

Enjoying this article? Sign up for our FREE newsletter!

A Space-Saving Solution

Unable to access the wharf from the water, TRG designed a piled solution that would suit the site’s needs. This involved installing five-metre steel piles behind the walls, galvanised to BS EN ISO 1461:2022 for further durability, using smaller piling hammers to ensure minimal vibrations and disruption to the nearby railway bridge.

A back-tied solution consisting of high-yield steel deformed Type 2 Grade 500N/mm² (B500b) bars rebar reinforcement bars allowed for a shorter front pile, meaning wall repairs could be carried out within the narrow space available. With the wall now secure, TRG could focus on renovating the wharf itself. Blue brick coper, outfalls, mooring rings and service bollards were specified and placed on-site for use by boaters.

Dredging works were also carried out throughout the project to remove contaminated waste – including heavy oils and metals – and make the canal safe for the residents of Hayes Village. To ensure these hazardous materials were disposed of properly, TRG sourced specialist sealed lorries to transport waste loads from the site for treatment and disposal.

Completing the Canal

All works were completed by May 2024, resulting in a renovated 60m wall, which can be moored by the canal community while also offering a safe space for Hayes Village residents to walk on. For the TRG team working on the project, helping transform the once-abandoned factory and neglected stretch of canal into an idyllic waterside housing development has proved extremely rewarding.

“The UK’s history can be found in its waterways and the Grand Union Canal is no exception,” explains Ian Rothen, Founder of The Rothen Group. “This wharf was once an integral lifeline for the former chocolate factory, and it’s been fantastic to bring it back to its former glory.

“We’re thankful to the Barratt London team for engaging our marine engineering expertise for these works. By working closely with the developers and the Canal and River Trust, we have been able to meet the remit of a 60-year lifespan guarantee required in the developer’s planning permissions.

“As this was undoubtedly a challenging project with multiple factors to consider, achieving this goal is a great source of pride for my team and I. These works can be highly complex, and I would encourage developers with similar site concerns to engage specialist assistance when it comes to waterways.”

Stephen Pargiter, Technical Manager at Barratt London, said: “It has been a huge team effort, and I’d like to say a big thanks to The Rothen Group for their part in bringing the new canal wall together, especially under Joe Kiteley and his team. Generally, their attitude on site was always positive and they engaged well with the Barratt London site team to deliver a high-quality product. Overall, it has been a pleasure dealing with The Rothen Group and as I said before, huge thanks for your part in the overall redevelopment of the canal front.”