PERI solutions drive efficiency on Walsall Waste to Energy project

PERI solutions drive efficiency on Walsall Waste to Energy project
Written by Amy
  • Specialist contractor Careys is constructing the 40 m high concrete structure for the Walsall Energy Recovery Facility, using systems from PERI UK to solve key on-site challenges related to vertical access and mass concrete slab pours.
  • The solution combines PERI UP system scaffold to provide safe, fast, and level access as the structure grows, alongside the BECOSTOP permanent stop end system to efficiently form the 880 mm thick ground slab, replacing traditional timber methods.
  • The project highlights how modern, engineered systems deliver significant advantages in speed, safety, and quality over conventional methods, with the supplier-provided temporary works design for the stair towers further de-risking the process for the contractor.

The critical task of erecting the 40 m high reinforced concrete structure has been awarded to specialist contractor Careys, a firm well-versed in complex industrial builds.

The structure, which rises from 6 m below ground to 30 m above, presented a series of classic concrete construction challenges. To meet the demanding programme, Careys implemented engineered formwork and scaffolding systems to solve two key problems: providing safe and efficient vertical access throughout the build and forming a massive 880 mm thick ground slab.

Rethinking vertical access

As the structure grew, providing safe access for operatives to work on the formwork became a primary concern. With a final height of 40 m, the access solution needed to be robust, quick to erect, and consistently safe. At the project’s peak, ten PERI UP Flex Stair Towers were in use across the site.

According to Gilbert Kee, sales engineer at PERI UK, the choice to use a system scaffold over traditional tube and coupler methods was a significant factor.

“Our PERI UP system is a system scaffold, which means everything has set lengths and heights. All you need is a hammer to lock the equipment securely,” he explains. “This gravity lock system is incredibly easy to erect; you literally just drop the components in, strike it with a hammer, and it’s secure.”

Enjoying this article? Sign up for our FREE newsletter!

This method contrasts sharply with traditional scaffolding, which requires careful measurement and tightening of individual couplers with a spanner, a process that can be time-consuming and prone to human error.

A key benefit that saves significant inspection time on site is the system’s inherent levelness. “All the rosettes [connection points] are at a set height, so as long as the base is level, everywhere you go up, it’s going to be level,” notes Kee. “This means they don’t need a special inspector to check every flight.”

Furthermore, the supplier provided full temporary works designs for the stair towers, a move that de-risks the process for the contractor. “An important factor in winning this project was the familiarity Careys has with our equipment,” Kee adds. “Because we do the temporary works design, the liability for the stability of the stair tower is on us, which simplifies things for them.”

Solving the stop end problem

On the ground floor, the project team faced the challenge of forming a huge 20 m x 20 m concrete slab with a thickness of 880 mm. A pour of this volume cannot be done at once, requiring robust stop ends to segment the pour into manageable sections.

“Traditionally, timber and ply would be used for this, which is a lot of work cutting and propping,” Kee says.

Instead, the project used the BECOSTOP system, a bespoke, permanent stop end solution. This engineered alternative arrives on site built-to-measure, ready for immediate installation.

“With our BECOSTOP system, erection is much quicker. Crucially, it’s left in position after the pour, unlike traditional methods where everything has to be removed,” Kee highlights. This single feature eliminates a significant amount of labour and material wastage associated with striking timber shutters. The system is also designed to allow reinforcement to pass through, ensuring continuity between pours. “It results in a very tidy build with minimal bleeding of concrete.”

William Griffith, project engineer at Careys, commented, regarding the labour-saving and safety benefits of BECOSTOP: “We used BECOSTOP for circa four months whilst constructing the Process Level Raft slabs. The reduction in the labour intensive striking of stop ends was a benefit to the project. Due to the reinforcement detailing and the reinforcement projecting so far past the stop ends there was also a safety benefit in the use of BECOSTOP due to not having operatives getting beneath the projecting reinforcement and in some cases into the reinforcement cage to strike a typical stop end in this scenario. This is, therefore, a huge advantage to de-risk the stop end striking activity.”

By implementing these engineered solutions, Careys was able to directly address specific site challenges, enhancing productivity and safety while reducing labour costs and material waste. The Walsall project serves as a clear example of how moving away from traditional methods towards integrated, system-based solutions can pay significant dividends on complex concrete structures.