Glounthaune to Midleton

Glounthaune
Written by Roma Publications

Glounthaune to Midleton Tracking


Iarnród Éireann has announced that the main construction work on the €90 million second track to Midleton is now largely complete, marking a significant milestone in the Cork Area Commuter Rail Programme.

Works began in September 2024 with an initial 12 months of preparatory works, including the laying of the new track bed and repositioning of the existing single track. The first piece of the new track was then laid on programme in September 2025, with construction progressing steadily since.

Project works also included the widening of the Owennacurra River Bridge in Midleton, as well as works to several culverts, level crossings, cuttings and embankments to accommodate the new track. All construction was carried out alongside a live operational railway line, helping to minimise disruption to existing rail services throughout the project.

In addition to the installation of 7.5km of new track and repositioning of the existing track, the project has also:

  • Moved more than 94,000T of earth and removed more than 8,750T of rock
  • Constructed 20 retaining walls along the track
  • Installed more than 10km of drainage
  • Laid more than 83,000T of track formation

While track laying is now largely complete, overall project completion will be in 2027, in line with the completion of the re-signalling of the full Cork rail network.

Phase 1 Cork Area Commuter Rail Programme

Phase 1 of the Cork Area Commuter Rail Programme incorporates the new €23 million platform 6 at Kent Station, together with the Glounthaune to Midleton twin-track and Cork area signalling and communications upgrade projects.

This phase will deliver the network capacity required to allow for a significant increase in train service frequency on each of Cork’s three commuter lines: to Cobh, Midleton and Mallow. Phase 1 will be fully complete in 2027.

Phase 2 Cork Area Commuter Rail Programme

Phase 2 of the Cork Area Commuter Rail Programme will provide eight new stations, a new depot, electrification of the network and, with the delivery of a new fleet, will ultimately support up to a 10-minute rail service frequency on each of Cork’s three commuter rail lines.

The second Public Consultation on Phase 2 was held in May 2026, with lodgement of a Railway Order Application to An Coimisiún Pleanála expected at the end of 2026.

Now designated critical infrastructure, Iarnród Éireann will be able to accelerate delivery of this transformative package of projects, bringing a high-capacity, high-frequency and more sustainable rail network to Cork more quickly.