Northern Line Extension
The Northern Line Extension (NLE), which is due to be completed in autumn 2021, is the first major Tube line extension since the Jubilee Line in the late 1990s.
The NLE between Kennington and Battersea will help regenerate the Vauxhall, Nine Elms and Battersea areas by supporting new jobs and homes. Two new stations are being built at Nine Elms and Battersea Power Station. The joint venture Ferrovial Agroman Laing O’Rouke is designing and building the NLE.
Main tunnelling finished in November 2017 after two tunnels were created between Battersea and new shafts at Kennington Green and Kennington Park.
The NLE will improve transport links and public spaces in the Vauxhall, Nine Elms and Battersea area, a designated regeneration area on the South Bank. Up to 25,000 jobs and 20,000 new homes could be created. Journey times from Nine Elms or Battersea to the West End or the City will, in some cases, be less than 15 minutes.
An independent report on the economic impact of the NLE has shown it could generate substantial benefits to the area. The extension is supported by the Mayor of London and Wandsworth, Lambeth and Southwark councils.
Updates
Towards the end of March all NLE construction sites were brought to a ‘Safe Stop’ in line with TfL coronavirus guidelines. However, this was not before TfL was able to announce that the new tube station at Battersea Power Station had received its first roundels.
In total, 113 roundels are being manufactured for installation at the two new Northern Line Extension stations, which are scheduled to open in autumn 2021 – 62 for Battersea Power Station and 51 for Nine Elms.
The arrival of the new roundels signifies an important milestone in the construction of the Northern Line Extension. The new roundels, among the most recognised and imitated logos in the world, are being manufactured at family-owned AJ Wells & Sons Ltd on the Isle of Wight where London transport signage has been produced for generations. They are the first roundels to be manufactured for a new Northern line station since the opening of the extension to Morden in 1926.
Heidi Alexander, London’s Deputy Mayor for Transport, said:
“It’s really exciting to see roundels now in place at Battersea Power Station – it makes the opening of the extension next year feel so much closer. These are the first new Northern line roundels in nearly 100 years and their arrival brings to life the huge difference the extension will make – easier journeys for thousands of Londoners, as well as supporting the creation of new jobs and homes in our city.”
With work now gradually resuming to site, focus has turned to power, cabling, door installation, fire prevention and testing and commissioning.
Tunnel Completion
Central to the success of the project so far has been the use of tunnel boring machines. In 2017 the NLE moved a significant step forward as tunnelling work to extend the line to Battersea began. Two giant tunnel boring machines, known as Helen and Amy, were lowered 20 metres below ground in Battersea in February. Helen began her 3.2km tunnelling journey a few months later in April while Amy set off in May.
Six months later a major breakthrough was achieved as Amy broke through at Kennington, meaning two 3.2km tunnels from Battersea Power Station have now been built. As the 100 metre long tunnelling machines advanced forward, nearly 20,000 precast concrete segments were put in place to form rings to line the tunnels.
The first train successfully travelled the length of tunnels last year, marking the completion of the tunnels and track.