Terzo Valico – Genoa Junction
WeBuild, Italy’s biggest infrastructure group, is developing a number of major public works in Italy, among which is the Terzo Valico dei Giovi, a new high-speed, high-capacity railway that will be 53 kilometres long and improve connections between the Liguria port system and the main railway lines of northern Italy and the rest of Europe.
The railway, with which 36 of its 53 kilometres will be underground, will reduce the time it takes to travel by train between Genoa and Milan to 50 minutes from one hour 39 minutes. It will be part of the Rhine-Alpine Corridor of the Trans-European Transport Network (TEN-T). In addition to the construction of the main line, the project includes four connections among Voltri, Genova Parco Campasso, Novi Ligure and Tortona in order to connect the line to existing ones.
The project recently saw two major breakthroughs along the two most important underground sections of the railway: the Valico Tunnel (Galleria di Valico) and the Serravalle Tunnel (Galleria dei Serravalle). Once completed, the Valico will be the longest railway tunnel in Italy.
The double breakthrough has allowed for work sites to be connected along a section of 17 kilometres. The first breakthrough done by the traditional excavation method occurred along the Valico Tunnel. It was the first of a number of breakthroughs that will occur along the planned tunnel’s entire length of 27 kilometres. It hosts the Camerone di Valico Nord, an underground cathedral of sorts covering 540 square metres, measuring 30 metres in width and 22 metres in height.
The second breakthrough was along the Serravalle Tunnel, with 6.4 kilometres of its 7 kilometres in total length already excavated by tunnel-boring machine. At work was a TBM baptised ‘Giovanna,’ 115 metres long with a diameter of nearly 10 metres. Its underground journey saw it cross complicated terrain near the Serravalle Designer Outlet and the old Genoa-Turin railway that required the use of an innovative monitoring system above and below ground.
The infrastructural upgrading of the Genoa Railway Junction, a strategic accessory to the new high-speed/high-capacity line, will ensure the connection of the last mile between the Terzo Valico dei Giovi and the historic Port of Genoa, allowing for a direct connection for freight trains in departure and arrival from the port. It will also separate traffic flows between regional trains and long-distance trains, with a consequent potential increase in the offer of regional and metropolitan trains.
The Genoa Railway Junction project involves completing the civil works of the Colombo, San Tommaso and Polcevera tunnels, with works lasting 30 months. With the Terzo Valico dei Giovi and Campasso freight yards, it is part of a unified project, worth almost €6.9 billion, with which it intends to act as a propelling force for the new railway between Genoa and the Po Valley, which has currently reached 40% completion.