Work has continued throughout 2020 to enable the commissioning of the railway between Bedford and Kettering/Corby.

Extensive work has already been carried out on this part of the route as part of the Midland Line Upgrade and has included:

  • New switches and crosses south of Kettering station which allows trains to connect to other tracks and to the main line to an electric stabling facility, which is being constructed near Kettering Station – all four tracks are now in place at Kettering sidings. This has involved 1,425m of new plain line track and will supplement the Electrification of the MML by providing a stabling facility for the new electric trains.
  • 23km of new track has been laid to produce the fourth line.
  • 5km of embankment works have been carried out.
  • 15 structures have been strengthened.
  • 105 new signals have been installed and 11 new signal gantries.
  • Stations have also been upgraded as part of the programme in preparation for the fourth line and electrification, by building and extending platforms and adjusting canopies to accommodate overhead cables.

The benefits of the fourth line

The benefits of the additional line will add capacity to the route, enabling longer trains with more seats between Corby, Kettering and London St Pancras. In addition, it will create the capability for six trains to London St Pancras per hour, up from the current five by the end of 2020. This will create additional resilience to the operational railway and improved timetables as a result of the additional line will allow for a second train per hour for Corby to be introduced.

In addition to the introduction of the fourth line, a series of possessions throughout 2020 have been required to prepare for energisation of the line between Bedford and Kettering/Cory. The first section was successfully energised on 26th July 2020 with further closures throughout the summer to complete the programme. Other essential works also took place during these closures.

Electric trains are quieter, meaning less disruption for lineside neighbours and wildlife; and they produce fewer emissions at the point of use – which means they don’t contribute to local air quality issues often found in urban areas. Electric trains are also lighter, meaning they need less power to do the same journeys. The power supply for electric trains is supplied by the National grid and an ever increasing amount of this power is being produced by renewable and low carbon technology, which means less fossil fuel and less emissions, and that means our railways are becoming more environmentally friendly.

Bridges

Network Rail has also undertaken 12 bridge reconstructions to allow clearances for the Overhead Line Electrification (OLE) as part of the electrification of the Midland Main Line from Bedford to Corby. This includes the successful completion of clearance work at Station Road Isham, Finedon Road Bridge, Wellingborough Viaduct, Irchester Viaduct and Cottingham Road Bridge. Network Rail is also working on Bromham Road Bridge and Irthlingborough Road.

As part of the ongoing works, track renewals and track installation is also ongoing and it is hoped that the line will be electrified by the end of December 2020.

 