Following a strong and very productive finish to 2021, Crossrail remained on track for the Elizabeth line to open on 24th May 2022. There was great momentum across the programme to complete the railway so passenger services in the central section, from Paddington to Abbey Wood can commence.
The final stage of the programme, Trial Operations, involved operational exercises to ensure the safety and reliability of the railway for public use and to fully test the timetables. More than 150 scenarios were carried out through the Trial Operations period to ensure the readiness of the railway for passenger service.
It took several months to complete Trial Operations. The Elizabeth line is an immensely complex railway and Trial Operations continued until it is clear that the railway can operate at the highest levels of safety and reliability before the start of passenger services.
A phased approach to Trial Operations was adopted to build greater resilience into the railway and to allow for the earliest commencement of passenger services. The first phase of Trial Operations commenced on the 20th November 2021, in line with the earliest forecast dates, and progressed well, with the majority of exercises passing but with comments. These comments provided key learnings for the programme as the service and systems were modified ahead of passenger service.
The successful commissioning of various system software over the festive period and the recent handover of Canary Wharf station to TfL allowed for the commencement of phase 2 of Trial Operations on the 28th January 2022. This phase involved a range of organisations, including TfL and London Underground, MTR Elizabeth line (as the operator), and Network Rail collaborating on the response to trial scenarios along with thousands of staff volunteers. Emergency services including the British Transport Police, London Fire Brigade and London Ambulance Service were also involved, demonstrating how they would respond to incidents on the network and in stations.
Nine of the ten new central section stations have now been commissioned and transferred to Transport for London with Canary Wharf the latest station to be handed over on the 21st January 2022. This meant that the station could be fully integrated into the operational network ahead of the line opening. It was the penultimate station to be handed over to TfL, with works remaining at Bond Street. The opening of the railway is independent of whether Bond Street station is ready for use by passengers.
Shobi Khan, CEO, Canary Wharf Group, said: “It’s fantastic to see the completed Canary Wharf station handed over to TfL, as the Elizabeth line gets ready to start operations. The Elizabeth line will be a game changer for London and for Canary Wharf. Residents, workers and visitors to Canary Wharf will benefit from fast, comfortable new trains, transforming connectivity and journey times across the capital.”
Opening the Elizabeth Line
In the first half of 2022, the Elizabeth line has launched with a new passenger service between Paddington and Abbey Wood, through new tunnels under central London. The launch will bring immediate benefits to passengers travelling between these stations with 12 trains per hour, in each direction, all day.
The opening of the Elizabeth line has always been planned to take place in stages to ensure the new central London stations, signalling and infrastructure can run safely and reliably before it fully links in with services out to the east and west.
The Elizabeth line will operate 12 trains per hour between Paddington and Abbey Wood from Monday to Saturday 06:30 to 23:00. Work will continue in engineering hours and on Sundays to allow a series of testing and software updates in preparation for more intensive services from the autumn.
Following the opening of the central section between Paddington and Abbey Wood and until the next phase of opening in Autumn 2022, the Elizabeth line will operate as three separate railways. The services on the east and west will continue to run into the mainline stations and passengers wishing to continue their journey to one of the new Elizabeth line central London stations will need to change between Paddington or Liverpool Street mainline and Elizabeth line stations.