For safety reasons, manufacturers, distributors, and operators must demonstrate that their trains are able to safely pass defined curve radii above the approved maximum speed. However, suitable route sections for these tests are few and far between. TÜV SÜD Rail and Munich-based company RailAdventure have broken new ground.
The approval of a Scandinavian high-speed train involved the performance of numerous tests and verifications. Where cross-border interoperability of the trans-European rail system is concerned, one of the key requirements is compliance with the Technical Specifications for Interoperability (TSIs), which define the requirements and test methods for components and sub-systems.
In accordance with TSI requirements, trains must be able to navigate the defined curve radii at speeds of up to ten per cent above the maximum target speed for approval and at increased lateral acceleration. Successful completion of the test represents proof of compliance with the required safety tolerances for the forces acting on the track during regular service. In the case of the Scandinavian train, approval for a maximum speed of 245 km/h was being sought. Given this, the train had to navigate curves with radii of less than 3,000 metres at speeds of approximately 270 km/h. The hunt for a suitable test route proved a challenge, but finally three curves that met the requirements of the standard were found in Germany.
Simulations and on-track tests for Scandinavian train
For the test, RailAdventure GmbH – a company specialising in performing test runs in rail traffic – had to demonstrate to the rail-network operator that it was safe to exceed the maximum speed allowed on the route sections. Speed limits on rail lines are intended, among other things, to protect the overhead line. To furnish the required evidence, TÜV SÜD Rail commissioned extensive simulation analyses and worked with the pantograph supplier to adjust the settings and optimise the design of the power collector in such a way that the contact forces never exceeded the level at the approved speeds, even at the point of the most critical uplift.
In the runup to these activities, track test vehicles travelled the route to find the most critical point in the overhead line. After that, the contact wire uplift was monitored at the most critical point using a sensor and the contact forces were measured along the entire test track. As high speeds have a strong influence on the contact force. The special aerodynamic optimisation of the pantograph was crucial to ensure the contact force between the contact strip and the contact wire could be precisely set for the test runs.
Finally, the test runs were undertaken in single traction with a single pantograph, thus minimising the wave motion of the overhead contact line compared to a run conducted with multiple raised pantographs. In total, all these measures enabled successful on-track testing without imposing excessive loads or stresses on the pantograph, the contact line, or the route, thereby paving the way for successful approval of the Scandinavian train. The project has shown that manufacturers, dealers and operators of high-speed trains can benefit from a wider choice of possible test tracks if they bring in the necessary expertise and work together closely coordinated and goal-oriented.
Dr.-Ing. Thomas Noack
TÜV SÜD Rail GmbH
thomas.noack@tuvsud.com
www.tuvsud.com/de-de/branchen/infrastruktur-bahn/bahn/dienstleistungen-fuer-schienenfahrzeuge
Dipl.-Ing. Jörg Schurig
RailAdventure GmbH
joerg.schurig@railadventure.de
www.railadventure.de