Progress has been made across both the HS2 projects of Chiltern Tunnels and Colne Valley Viaduct. Greenlit back in 2021 with a peak overall budget of £965 million, these constructions are part of High Speed 2’s plans to improve the railway links between London and Birmingham. The main contractors are Align JV, and around 1,200 people make up the design and construction teams.

Chiltern Tunnels

As of February 2023, the site saw ‘Florence’ and ‘Cecilia’, the two huge tunnelling machines, reach the halfway mark of their 10-mile excavation beneath the Chilterns. Since 2021, these 2,000-tonne machines have been creating two parallel tunnels towards South Heath in Buckinghamshire from the M25 to establish a new, environmentally friendly link between London, Birmingham, and the North of England. The machines have displaced more than 1.3 million cubic metres of chalk and flint during their journey so far – enough to fill over 500 swimming pools.

Engineers have also confirmed the completed excavation of five ventilation and emergency exit shafts positioned at multiple points along the route, including Amersham and Chesham Road.
In August 2022, a new phase of construction began on thirty-eight cross passages between the northbound and southbound tunnels. A team of miners are using remotely controlled excavators to break through from one tunnel to the other, utilising sprayed concrete lining (SCL) as they progress to maintain the structural integrity of the ground.

The Chiltern tunnels project was launched back in the summer of 2021 to create space for the longest tunnel on the HS2 route. Each tunnel – reaching almost 16 kilometres in length – will be blended into the landscape, reducing environmental damage and limiting the disruption to the local area as passengers journey across the Chilterns at speeds of up to 200 miles per hour.

Colne Valley Viaduct

Last spring, the 700-tonne launching girder known as ‘Dominique’ was brought onto the site to begin construction on the viaduct bridge. The only one of its kind in the UK, this machine lifts and positions the giant concrete deck segments which make up the viaduct’s arches. A thousand of these segments are due to be placed by the machine, each weighing around 140 tonnes, with a pair of them being installed every 36 hours. Due to the contours of Colne Valley, each individual deck segment needs to be uniquely shaped in order to fit correctly and safely.

Supporting the viaduct will be a series of land piers – built with faceted formwork above bored piles – and V-shaped water piers. These latter piers require pile caps to be cast within temporary cofferdams, and eleven are needed for the project. One has been fully constructed to date, and the average construction time for one of these piers is between seven and nine months.

Work has also begun on an entirely new phase of the project – the bridging of the A412. Installing the deck segments which are due to support the viaduct as it passes over the road will require nightly road closures to limit disruption. This section looks to be completed by late 2024.

The Colne Valley Viaduct is one of the most challenging stages of the HS2 megaproject, with difficult terrain and water features needing to be navigated in order to complete the 3.4-kilometre-long structure. Work began in 2021 with the construction of 292 foundation piles, and this stage was confirmed to have concluded at the end of January 2023. Upon completion, the viaduct will have 56 pier supports with an average height of 8.7 metres each, making it the UK’s longest railway bridge.