Edinburgh Tram Extensions
This summer, the Edinburgh Trams network underwent a £200 million extension project to make the transport system more accessible to thousands more people across the city. Continuing with the momentum of the successful scheme, Edinburgh Trams are now developing new plans to implement further extensions and create a game-changing North-South tramline.
The latest improvements to the Scottish capital’s tram network saw it extended by 3 miles to form a ‘spine’ throughout the city, facilitating services from Edinburgh Airport, Gyle Centre, Edinburgh Park, and Murrayfield Stadium. An additional 8 stops were constructed across the city centre – including Leith Walk, The Shore, Ocean Terminal, and Newhaven – and have been strategically placed to improve the convenience of tram travel for thousands more people.
The project involved the embedment of 2.9 miles of twin track and the construction of two new substations with associated switchgear and transformer rectifiers supplying 750v line voltage. Once installed, the new line underwent stringent software and signalling tests as well as half and full speed tram tests. The final stage prior to opening saw the extension incorporated into Edinburgh Trams’ control centre.
The completion of this extension marks a significant milestone for the Edinburgh Tram network as it sees Leith reclaim its role in the tram network for the first time since 1956. Plans to develop a tram route through Leith to Newhaven were originally drawn up nine years ago, however revisions brought about due to budgeting concerns meant this section of the project was scrapped.
Following this success, Edinburgh Trams are planning to extend the tram network again to Granton, an area of the city currently experiencing a £1.3 billion regeneration programme. Similar to Leith, plans to include Granton via Haymarket were drawn up and abandoned as part of previous projects, however the development of thousands of new homes in the area has spurred new interest in connecting it to the network. The Granton Waterfront development is predicted to boost the population and economic growth of the area, making a tram stop a necessity for the future.
Also part of the plans is a new north-south tramline connecting the city centre to Edinburgh Royal Infirmary. A similar project was proposed in 2001 but lacked the required funding, however new proposals are being made to connect this idea with the Granton tram stop to create a new route connecting Little France with the city centre, Granton, Dalkeith and beyond.
Such an extension will not only provide the obvious benefit of delivering a direct route to the hospital for those attending appointments, but it will also reap economic benefits from connections with the development of the BioQuarter, a groundbreaking new medical research and health innovation complex.
A three-month consultation is due to take place later this year to further assess the viability of the project. A primary question this process will look to answer is whether the extension ought to be carried out as originally planned along the Roseburn cycle path, or be developed via Orchard Brae, allowing the cycle path to be protected.
Current projections suggest the new north-south tram line between Granton and Dalkeith will be ready for passengers in 2035. Although distant, the project’s completion looks to bring the benefits of the Edinburgh Trams network to even more people across the city, such as regular services departing every 7 minutes, CCTV systems and customer help points, and easy-to-use ticketing processes both in person and via the Edinburgh Trams app.