HS2 Bromford Tunnel
Bromford Tunnel is a 3.5-mile (5.6km) twin-bore high-speed rail tunnel. Two huge tunnel boring machines (TBMs) are being used to dig it between Water Orton in North Warwickshire and Washwood Heath in Birmingham.
TBM Mary Ann is digging the first bore and was launched in August 2023. TBM Elizabeth is digging the second bore and was launched in March 2024. The tunnelling operation is being delivered by around 450 people working around the clock. Each bore will take around 16 months and 1.87 million tonnes of material will be excavated and sifted at the on-site slurry treatment plant to be reused on nearby sites at the Delta Junction.
The eastern portal (Water Orton)
The eastern portal of the tunnel will be located off Attleboro Lane in Water Orton. The design of the portal is ongoing, and local communities will be kept up to date as the design progresses.
A compound will be used to construct the tunnel; to store materials and serve as a base for the workforce and this will be accessed via purpose-built haul roads. The previously proposed substation is now being progressed at a different location off the Birmingham Road.
To minimise the noise of trains as they exit the tunnel, the team will be constructing a porous portal. On high-speed railways the purpose of a porous portal is to ensure that the waves produced by the ‘piston effect’ of the train moving at speed, which can otherwise result in noise as the train exits the tunnel, are kept at a level that does not adversely affect the surrounding area. A porous portal is generally achieved by providing perforated structures, usually of concrete, at the tunnel entrances.
The western portal (Washwood Heath)
The 22-metre-deep western portal at Washwood Heath has been finished in readiness for the two 1,600 tonne tunnel boring machines (TBMs) building the twin-bore tunnel to complete their journeys from Water Orton in North Warwickshire.
The huge earthworks operation has taken a team of 130 people nine months to complete. Mary Ann, the first TBM to launch from Water Orton in 2023, is expected to break through into the portal by the end of 2024, with the second TBM Elizabeth set to finish her drive by autumn 2025.