East Kilbride Enhancements
The East Kilbride Enhancement Project is part of the Scottish Government’s wider plans to decarbonise passenger services across Scotland’s Railways.
At the heart of the plan is the electrification of routes, and introduction of electric trains, to enable carbon free journeys for communities along the East Kilbride to Glasgow railway corridor. The £139.8m project is at the centre of the Scottish Government’s Rail Services Decarbonisation Action Plan, and will provide passengers in Scotland with quieter, greener and cleaner trains, resulting in healthier and more pleasant journeys for all.
Reducing the carbon emissions of rail journeys helps to improve air quality and plays a vital role in building a strong, green economy for the future.
The East Kilbride Enhancements Project began in early 2024, and following completion of site set up in February 2024, a 16 month construction programme began, which included the Hairmyres station and the accessible new building at East Kilbride station. An 11-month programme of piling and steelwork installation between Busby and Thornliebank stations also began, which was completed in December. A 9-month programme of piling and steelwork installation between East Kilbride and Thorntonhall began in March 2024 and was also complete in December.
Works to replace the Thornliebank Road bridge on the B769 began in September and is planned to continue into June 2025. From 28 September to 01 October 2024 the Thornliebank Road bridge and Westerton Lane footbridge, near Busby station was removed, in anticipation of their replacement. The bridges need to be replaced in order to allow enough space underneath to install the new overhead line equipment. In preparation for the demolition works, the footbridge that serves the footpath between platforms 1 and 2 at Thornliebank station was removed overnight on Saturday 21 September, with a diversionary route provided for passengers via a temporary footbridge. A new accessible bridge was also craned into position at the new Hairmyres station. Along the route, drainage works, and the installation of new overhead line equipment has also been completed.
From mid-September preparatory works have also been underway at Giffnock station, in advance of a new, accessible footbridge which will be installed in early 2025. Part of these works involved removing vegetation adjacent to Platform 2 in order to create a safe working area for the installation works next year. It is anticipated that the existing station footbridge will remain in use until it’s replaced by the new structure next year.
Piling works also took place throughout October until the end of 2024, in order to install the foundations that will support the new footbridge. The site compound already in place at Giffnock station was expanded, utilising 68 parking spaces to allow for extra space to ensure the safe mobility of plant and machinery. The remainder of the station’s parking spaces are still available, including accessible spaces.