Limerick to Foynes Frieght Line
As part of the Iarnród Éireann Irish Rail Rail Freight Strategy 2040, working with their colleagues in the Shannon Foynes Port Company, Iarnród Éireann are planning to deliver a reliable, frequent and sustainable logistics option for the many companies that currently or in the future will use the port of Foynes.
The 42km stretch of railway between Limerick and Foynes originally opened in 1858 but has been inactive since 2001. The line remains under the stewardship of Iarnród Éireann and will now be renewed to support the reintroduction of rail freight services on the line.
Under the Iarnród Éireann Rail Freight 2040 Strategy, Iarnród Éireann is committed to positioning rail at the centre of Ireland’s freight transport system, creating connections and giving greater opportunity for business to switch from road freight to more sustainable rail freight.
The line regeneration, while initially for rail freight services, will not preclude the possibility of passenger services being reintroduced on this line in the future subject to further infrastructure upgrades and funding.
Key project elements
Phase One of the project, funded by the Department of Transport, involved the following works:
- Vegetation clearance and removal of existing track.
- Replacement of track formation and installation of a new ballast bed to current Iarnród Éireann standards.
- Rehabilitation and / or renewal of bridges and culverts.
- Supply and installation of new rail and concrete sleepers along the entire route.
- Renewal of road infrastructure at public road level crossings.
- Renewal of accommodation crossings.
- Renewal of lineside fencing.
- Installation of infrastructure to accommodate the next phase of the project.
Latest updates
Iarnród Éireann is now a step closer to the reintroduction of freight services on the Limerick to Foynes rail line, as the laying of 42km of new track is now complete. During the past 27 months, Iarnród Éireann, along with project partners Sisk, have completed the removal of all original rail line infrastructure, followed by a complete renewal and relaying of 42km of track, sleepers and track bed.Other key elements undertaken by this €151.5 million project to date include.
- The removal, restoration and reinstatement of the River Maigue and River Deel bridges.
- Construction of a new 46m span bridge to replace Robertstown Viaduct.
- The upgrading and reinstatement of 13 public road level crossings.
- Installation of duct and drainage routes.
- Renewal of user worked level crossings.
- Boundary fencing works as required along the length of the line.
Next steps
The line is planned to come into operation in 2026. The project now enters its next phase with works to be undertaken over the next 18 months including:
- Specialist in house teams delivering the signalling & telecoms infrastructure to enable trains to operate.
- Closure of user worked level crossings by structures.
- Refurbishment of Foynes Station building.
- Installation and testing of CCTV at the 13 public road level crossings – a significant safety improvement over previous gated crossings.