Darlington Station
Tees Valley Combined Authority, Darlington Borough Council and London North Eastern Railway are upgrading Darlington Station by proving new facilities including two new platforms on the Eastern side of the station and a new, fully accessible and enclosed footbridge linking them to the current station.
The upgrades also include new cycle lanes, bike shelters and a multi-storey car park which will adjoin the new station building. The car park will include secure parking for over 600 cars including accessible parking bays and electric car charging points.
Due for completion by the end of 2025, the package of upgrades will not only transform station facilities for passengers, but it will also provide a new integrated transport hub to improve the regions local and national transport links.
The two new platforms will provide passengers with a better service and more travel options in the future. They will also improve reliability and reduce delays for both local and long-distance high-speed services on the East Coast Main Line, both for now and in the future.
The project is designed make the station easier to use for people arriving by public transport or on a bicycle. The station will also be fully accessible for those with additional access needs, limited mobility, families with pushchairs and those struggling with heavy luggage, with step-free access throughout the station.
Platforms 5 & 6
In Autumn 2024 work began on the build of the new railway track so that more trains will in future be able to serve them. The railway needs to be adapted to the south of Darlington station where they branch onto the Bishop line.
Work includes new foundation stone, known as ballast, laid, new track and switches and crossings – the moving section o f the track which allow trains to change lines – installed.
Modern Pedestrian Eastern Gateway ‘link bridge’
A 50-toone footbridge has been installed linking the existing grade II listed station with the new platforms 5 and 6 and eastern concourse building.The bridge was fixed into place after arriving on Friday 21 February 2025 in two parts – one weighing 32 tonnes and measuring 31 metres in length, the other 18 tonnes and 16 metres.
A hole had to be created in the Victorian station’s roof to allow the bridge to slide into place – using a 750-tonne crane which was purpose built at the site by a smaller crane.
Smithfield Road Railway Bridge
The teams involved with the project have completely rebuilt the railway bridge which takes trains over Smithfield Road to the south of Darlington station. This is part of the track layout improvements which have been undertaken so more trains can serve Darlington station in future. This work took place throughout 2024 with work completed in November of that year.
Inside the existing station
Work is ongoing inside the existing Grade II listed building for the new fully accessible footbridge, lifts and staircases, with ongoing foundation works for the new steel structures. This is all happening behind the timber hoarding on Platform 1 inside the station. Work on this aspect of the project is due to complete in Autumn 2025.
The Darlington Station upgrade project has a target completion date of December 2025 – a fitting close to this year’s Railway 200 celebrations marking the 200th anniversary of the first passenger journey.