Major work to rebuild a railway bridge in Stockport has completed with further works to the site due to be completed by Spring 2026.

The Greek Street bridge was demolished and rebuilt over 21 days between 2nd and 23rd August 2025 as part of a £20m Network Rail investment to benefit both the road and rail network. The 21-day blockade was a unique feature of the scheme that had never been attempted at this scale before in Stockport. By closing the railing, it allowed the team to safely and efficiently carry out complex tasks that would otherwise take months.

The original bridge, which was constructed in 1958, had put in 67 years of service but needed to be replaced with a modern structure which will last for up to 120 years. The bridge, which is on the Manchester spur of the West Coast Main Line sees about 400 passenger and 50 freight services passing under it each day.

The bridge project was complex and huge with more than 2,500 engineers working on site with over 100 staff on shift each day. The bridge replacement, which has been replaced with a single span structure that is simpler to maintain and make it more resilient in the long term included:

  • Replacing 181 bridge beams across the 60 metres by 27 metres bridge.
  • Removing and then reinstalling over 1,000 metres of overhead lines that power electric trains.
  • Laying 1,800m² of protective decking over the railway track.
  • Four cranes to demolish and replace the bridge.
  • 220 wagons to move materials around the site.
  • Over 500 hours of work.

William Brandon, Network Rail’s project manager, said: “The work to strengthen Stockport is a once-in-a-lifetime opportunity to make train journeys on the Manchester spur of the West Coast Main Line safer and more reliable.”

As part of the project, Murphy, the contractor working on behalf of Network Rail, worked closely with utility companies to safely divert important services, such as water and electricity, out from below the road service and into a temporary bridge. This complex operation made sure local communities had access to everything they needed during the work. With the new bridge now in place, the utility services which were diverted are now being reinstated. The road is also being rebuilt and once completed the Greek Street Roundabout will reopen.

In early October the railway closed again to allow engineers to begin to reinstall part of the roundabout that sits on top of the bridge with further work planned over Christmas 2025.

In Spring 2026, Network Rail will complete the work to reinstate the road over the bridge and once this is complete, The Greek Street roundabout will then reopen.

For more information about the project, visit www.networkrail.co.uk/greekstreet.