Camp Hill Line Stations
Three new stations on the Camp Hill line opened to the public in April 2026, reconnecting the communities of Pineapple Road, Kings Heath and Moseley Village with Birmingham City Centre for the first time since the original line closed during World War II due to coal shortages.
Since the closure of the original stations, the local population has grown significantly, alongside an increase in commercial activity across the area. As a result, more people are travelling, contributing to traffic congestion and longer journey times on surrounding roads. The reopening of the Camp Hill line stations is set to provide residents and visitors with a faster, more sustainable transport option.
On behalf of Transport for West Midlands (TfWM), VolkerFitzpatrick was appointed principal contractor to design and build the three stations. Each station features two platforms capable of accommodating six-car trains, alongside pedestrian footbridges, stairs and lifts, ticket machines and information systems, passenger help points on every platform, and secure cycle parking facilities.
The project also incorporates links to the line’s heritage. At Kings Heath Station, the original King’s Heath station sign has been restored and reinstated at the entrance to the new station after being purchased from a private collector. Located on land adjacent to Kings Heath High Street, the new station sits on the site of its historic predecessor.
Pineapple Road Station has also been constructed on the site of the former station, adjacent to Cartland Road, and includes dedicated pick-up and drop-off facilities for passengers. Similarly, Moseley Village Station, located between Woodbridge Road and St Mary’s Row on the site of the original station, also provides passenger pick-up and drop-off areas.
Now complete, the new stations will significantly reduce journey times into Birmingham city centre. Estimated journey times to Birmingham New Street are:
- 14 minutes from Pineapple Road, saving between 16 and 31 minutes
- 11 minutes from Kings Heath, saving between 9 and 24 minutes
- 8 minutes from Moseley Village, saving between 7 and 21 minutes
Led by TfWM, part of the West Midlands Combined Authority (WMCA), and the West Midlands Rail Executive (WMRE), the stations form part of a £61 million investment programme. Funding included £36 million from the WMCA, £20 million from the Department for Transport, and a further £5 million from Birmingham City Council’s Clean Air Zone fund. Project partners also included Network Rail and train operator West Midlands Railway.
Construction work on the stations began in November 2022 and was completed in April 2025.