Carluke Station Footbridge


Work has begun on a £500,000 upgrade of the footbridge at Carluke Station in South Lanarkshire, as part of an investment to improve the condition, safety and longevity of the station’s infrastructure.

More than 5,000 people use Carluke station every week, with around 75 daily services helping to connect the town with Glasgow and destinations across the surrounding area. The footbridge is an important part of the station, providing a link between platforms 1 and 2 and helping passengers access their services.

The bridge is undergoing a programme of repairs to its concrete structure and supporting steelwork. As part of the upgrade, the existing lighting will be replaced, while new handrails and anti-slip surfaces will be installed on the stairs to improve safety for passengers. Paintwork will also be touched up where required, helping to protect the structure and improve its overall appearance.

In order for the work to be carried out safely, the footbridge closed on Saturday 15th August and is due to reopen on Saturday 14th November. During this period, passengers will be able to use a signposted diversion between the two platforms via the underbridge on Station Road. This is currently the accessible route for passengers who are unable to use the stairs.

Anthony Trodden, scheme project manager at Network Rail, said: “Footbridges are a vital part of stations, and it’s important we continue to invest in their upkeep. These improvements will extend the lifespan of the bridge, improve safety and help ensure the footbridge continues to provide a reliable route between platforms.

“We understand this may cause some inconvenience and would like to thank passengers and residents for their patience while these essential improvements are completed.”

Mark Ilderton, ScotRail Service Delivery Director, said: “We know how important footbridges are at stations and it’s essential they are in the best possible condition.

“These upgrades at Carluke station will make it easier for customers to move between platforms, enhancing their travel experience with us.

“We thank everyone for their patience while this vital work is carried out.”

The work will be phased to minimise disruption where possible. Between 15th August and 12th September, work will be carried out overnight from Saturday to Thursday each week. From 19th September to 14th November, overnight work will take place on Saturdays only.

The completed improvements will help ensure the footbridge remains safe, functional and reliable for the thousands of passengers who use Carluke station each week.